TRC Signs a ฿800Mn Contract of Highway Route No.41 Ban Mai Siap – Phatthalung Restoration

TRC Signs a ฿800Mn Contract of Highway Route No.41 Ban Mai Siap – Phatthalung Restoration


TRC Construction Public Company Limited (TRC) announced that Sahakarn Wisavakorn Co., Ltd. (SKW), its subsidiary had signed the construction contract with the Department of Highways on 17 September 2020 for the restoration of highway network connecting the region, Highway Route No.41, Ban Mai Siap –Phatthalung. The project focuses on construction and restoration of Asphalt Concrete Road including road lighting system, distance32.437 kilometers, with a contract value of 831.18 million baht. Construction period is 1,080 days.