All EA’s Hanuman Projects Have Achieved COD, Starting to Fully Recognize Income!

EA has announced that all of its "Hanuman Projects" have achieved COD.


Energy Absolute Public Company Limited (EA) has announced that the 80-MW Wind Power Plant (Project Hanuman 10) at Chaiyaphum province of EA’s Subsidiary (Banchuan Development Co.,Ltd.) has completely connected to power system of the Electricity Generating Authority of Thailand (EGAT) and commenced the commercial operation on April 13, 2019 : 12.00 hrs.

Consequently, the sale revenue is booked from April 13, 2019 : 12.00 hrs. onward. Therefore, EA concludes that all 5 Hanuman projects (Hanuman 1, 5, 8, 9, 10 projects, the aggregate capacity of 260 MW) have already achieved COD.